Renovation construction, from demo day to final clean-up day, is all dependent on your specific project’s scope of work. For example:
Hall Bathroom Pull & Replace: 2-4 weeks
All new tiling, shower system, toilet, vanity, lighting, accessories
Primary Bathroom Pull & Replace: 3-5 weeks
All new tiling, shower system, new tub system, toilet, vanity, lighting, accessories, etc.
Primary Bathroom Reconstruction: 4-7 weeks
Moving walls, plumbing, lighting, etc.
All new tiling, shower expansion, new tub (free standing), toilet, vanity, venting exhaust fan outside, add recessed lighting, etc.
Kitchen Pull & Replace: 2-4 weeks
Same layout: cabinets, new appliances, countertops, sink & faucet, hardware, etc.
Kitchen Reconstruction: 4-8 weeks
Move walls & plumbing, add additional recessed lighting, new cabinet layout, countertops, appliances, sink & faucet, hardware, etc.
Upgrading Finished Basement: 2-4 weeks
New flooring, built-in TV cabinets, kitchenette, furniture, etc.
Finishing Basement: 6-12 weeks
Framing, drywall, ceiling, staircase, electrical, plumbing, flooring, HVAC, cabinetry, appliances, etc.